Onerahi progress – Build Complete

The photo below is the bare section at Onerahi where three new 2 bedroom units will be built.

 

11th May 2024 – Fantastic to see the Earthworks being started at Onerahi whilst Glenbervie also continues… we have two new builds underway!

 

7th July 2024 – The building site now has an accessway and a building platform… boxing for concrete slab will be on the “menu”

 

16th August 2024 – Great to see the timber boxing in place for the concrete slab along with a privacy fence on the left of the section as you’re looking at the photos. The third photo looking down the driveway also shows how close and convenient the Onerahi shopping centre will be to these three units 🙂

 

26th August 2024 – Concrete slab in place for the 3 units… next will be the scaffolding.

 

10th September 2024 – The scaffolding is up and so is the framing and building paper!

 

15th December 2024 – Driveway created and exterior of units completed

27th of March 2025 – Building of Units completed… Hurrah! Now 3 more people can live INDEPENDENT lives with an accessible HOME 🙂